Unapproved designs can impact cost, delay project

Discussion in 'Tower Component, Lighting , Accessory Discussions' started by Wireless Estimator, Feb 1, 2008.

  1. Wireless Estimator

    Wireless Estimator Administrator Staff Member

    If you are going to provide an alternate waveguide bridge system make sure that the new design is approved by the A&E firm and included in the construction drawings prior to permitting. Although it seems like a small component of the overall tower system, some building officials will not close out the permit until such time as sealed drawings are provided for the new design. This can be a costly and time-consuming procedure.