Although many building departments fall in line with the below pricing recommendations for permit fees from the 1997 Uniform Building Code, it is suggested that you contact the jurisdictional building authority to identify their fee schedule. These fees are solely for issuance of the permit and do not include any plan review or other administrative charges.
$500 to $2,000, for the first $500
|
23.50
|
Each additional $100 or fraction, to $2,000 |
3.05
|
$2,000 to $25,000, for the first $2,000 |
69.30
|
Each additional $1000 or fraction, to $25,000 |
14.00
|
$25,000 to $50,000, for the first $25,000 |
392.00
|
Each additional $1000 or fraction, to $50,000 |
10.10
|
$50,000 to $100,000, for the first $50,000 |
644.00
|
Each additional $1000 or fraction, to $100,000 |
7.00
|
$100,000 to $500,000, for the first $100,000 |
994.00
|
Each additional $1000 or fraction, to $500,000 |
5.60
|
$500,000 to $1,000,000, for the first $500,000 |
3,230.00
|
Each additional $1000 or fraction, to $1,000,000 |
4.75
|
For 1,000,000 |
5,610.00
|
Each additional $1000 or fraction thereof |
3.65
|
|